PMP 기출문제 Q1476 해설 — Process
PM이 새 제품의 프로젝트 헌장을 받았다. 하드웨어(상세 사양)와 소프트웨어(기본 사양, UX 디자인 필요)의 두 주요 납품이 있다. 어떤 접근법을 권장하는가?
A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined, including a sample machine, and the user interface software that has only a basic specification and a requirement for a user experience design approach. Which project management approach should the project manager use?
- A.인도물이 크게 다르므로 프로젝트를 두 개로 분리한다 The deliverables are significantly different, so the project should be split into two projects that are driven by a program.
- B.범위가 잘 정의되어 있으므로 예측형 접근법이 직관적이다 The scope is well defined; therefore, a predictive approach is straightforward and the hardware and software can by synchronized on the gates.
- C.소프트웨어가 높은 불확실성이 있으므로 전체 프로젝트에 애자일을 권장한다 The software development has a high uncertainty level, so an agile approach is recommended for the project.
- ✓ 정답 D.하이브리드 접근법—소프트웨어에 애자일, 하드웨어에 예측형을 사용한다 A hybrid approach will work, using agile for software development and a predictive approach for the hardware deliveries.
정답: D
해설
하드웨어(상세 사양)와 소프트웨어(기본 사양, UX 필요)가 있는 프로젝트에서는 하이브리드 접근법을 사용해야 한다. 소프트웨어에 애자일, 하드웨어에 예측형이 각각의 특성에 맞다. 분리(A)는 통합을 어렵게 한다. 예측형(B)은 소프트웨어 불확실성을 다루지 못한다. 전체 애자일(C)은 상세 하드웨어 사양에 맞지 않는다.
When a project has hardware with detailed specifications and software with only basic specifications requiring UX design, the project manager should use a hybrid approach — agile for software development and predictive for hardware deliveries. This tailors the methodology to each deliverable's nature. Splitting into two program-driven projects (A) adds overhead. Using purely predictive (B) ignores software uncertainty. Using purely agile (C) is unsuitable for well-defined hardware.