PMP 기출문제 Q1576 해설 — Process

ProcessScopeFocus on ValueAgile

고정 예산 프로젝트에서 CEO가 팀의 절반을 기술 서밋 프레젠테이션 준비에 투입했다. PM은 무엇을 해야 하는가?

In a fixed-budget project, the team has received a prioritized list of requirements and has nearly completed the first iteration. The CEO has decided to redirect the team to focus on creating a presentation for their upcoming technology summit. The CEO is not flexible about this request. Which two actions should the project manager take? (Choose 2)

  • A.팀 재배치에 기반한 새 목표 완료일을 결정한다 Determine a new target completion date for the project based on the redirection of the team.
  • ✓ 정답 B.CEO에게 기능 팀원 일부를 프레젠테이션에 배정하도록 요청한다 Request the CEO to assign some of the functional team members to work on the presentation.
  • C.팀에 초과 근무하여 서밋 지원으로 잃은 시간을 보충하도록 요청한다 Ask the team to work overtime to make up the time lost by supporting the technology summit.
  • ✓ 정답 D.팀을 나누어 프레젠테이션과 프로젝트 작업을 동시에 계속한다 Divide the team to continue working on both the presentation and the project work.
  • E.프레젠테이션 작업을 혼자 완료하여 일정에 부정적 영향이 없도록 시도한다 Attempt to complete the presentation work alone so that the timeline is not negatively impacted.

정답: B, D

해설

CEO가 팀 절반을 프레젠테이션에 투입할 때, PM은 두 가지를 해야 한다: CEO에게 기능 팀원 배정을 요청하고(B), 팀을 나누어 프레젠테이션과 프로젝트를 동시 진행한다(D). 대체 자원과 병행 작업이 영향을 최소화한다. 완료일 변경(A)은 해결이 아니다. 초과 근무(C)는 번아웃이다. 혼자 완료(E)는 비현실적이다.
When the CEO redirects half the team to prepare a technology presentation, the project manager should take two actions: request the CEO to assign some functional team members to work on the presentation instead of the project team (B) to protect the project resources, and divide the team to continue working on both the presentation and the project work (D) to maintain progress on both fronts simultaneously. Requesting functional resources preserves the project team's capacity, while dividing the team ensures neither effort stalls completely. Determining a new target completion date (A) accepts the delay without trying to mitigate it. Asking the team to work overtime (C) risks burnout and may violate labor policies. Attempting to complete the presentation alone (E) is unsustainable and not the PM's responsibility.

전체 2,250문제로 실전처럼 연습하기

이 페이지는 공개 샘플입니다. 회원가입하면 전체 2,250문제 무제한 풀이 + 오답노트 + 영역별 정답률 분석을 7일간 무료로 이용할 수 있습니다.

무료로 시작하기 →